Section II.2.3: According to the ‘Planned Schedule for the Project Implementation’ set out on p. 11 potential bidders have already been requested to submit Expression of Interest. Does that mean that in parallel to the subject tender a pre-qualification process has already been launched? If yes, will the Consultant be provided wit

Yes, the process of hiring Transaction Advisors and Expression of Interest is in the parallel phase. On the second question, task 3.2 explains that the Consultant may be requested to evaluate the qualification statements of Prospective bidders and deliver a ‘Bidder Evaluation and Short list Report”, recommending a short-list of pre-qualified bidders to the Client.