Download the brochure of "Licensing and permitting requirements for renewable energy"
Steps to be followed and the institutions responsible for issuing licenses and permits for projects of renewable energy sources
Step 1
Kosovo Business Registration Agency (www.arbk.org)
- Business Registration
Step 2
Ministry of Environment and Spatial
Planning(http://mmph.rks-gov.net/)
- Environmental protection permit
- Water exploitation permit(if hydropower)
- Construction permit (above 20MW installed capacity)
Step 3
Permits depending on the construction location
- Kosovo Forestry Agency (if forest)
- Ministry of Culture, Youth and Sport (if special interest/
archeological zones)
Step 4
Ministry of Infrastructure (http://mi-ks.net/)
- Connection to existing road infrastructure permit
Step 5
Municipalities
- Construction permit(below 20MW of installed capacity)
- Contract for using the land
Step 6
KEK (www.kek-energy.com/)
- Authorization for connection to Energy Distribution System
- Contract of energy purchasing from suppliers. In case of
feed in tariffs, public supplier.
Step 7
Energy Regulatory Office (www.ero-ks.org/)
-Authorization for energy generation
Feed-in Tariffs
Feed-in Tariffs applicable for electricity produced from
renewable energy sources and admitted to the Support
Scheme.
Primary renwewabkle energy source
|
(/MW) |
HPPs (<10MW)
|
63.3
|
Wind
|
85.0 |
Solar Energy
|
j/a
|
Biogas and Biomass
| 71.3 |